Tower Time – Part 7 – Crane day

Ground crew bolts tower to foundation.
Crane holding tower on base

The weather which was forecast to be warm but wet, stayed warm and dry with an overcast sky, moderate winds and temp in the 50s.

Ground Prep

As the tower was assembled on the ground, the first order of business was installation of a cross arm assembly on the bottom of the structure. A much easier task once the crane was able to raise the structure to a comfortable working height.

Also visible in this image is the rotor, mast and thrust bearing which I had installed and tested during the previous week.

Cross arms being installed.
Tower lifted into a working position.

Lifting

A better view of the cross arm assembly which from the factory calls for three vertical masts. I elected to only use the two outboard positions and chose to install just below the 80ft height as I wanted to allow for 10 ft of vertical clearance from a WISP antenna which will be installed near the rotor plate.

IMG_3277
Mid lift

The slings were attached to the bottom rails using clevis shackles inserted into the unused step bolt holes in the bottom rails. These straps were then run through a larger clevis shackle above which would allow the lengths to shift as the assembly shifted to vertical.

IMG_3274
Lifting continues
IMG_3281
Almost there.
IMG_3283
Ready to swing over to the base.
IMG_3284
In the vertical for the first time

Winds were light, as the boom was swung around to the north the steps bolts which were on the up side while horizontal. Are now facing south and will need to be rotated to the north prior to landing.

IMG_3287
Ready to swing to the pad

Landing

Lowering and rotating to get the step bolts on the north side.

IMG_3288
Over the base

Speaking with the factory there are two ways to land this sort of tower, with the leg stubs attached to the tower or with the leg stubs attached to the foundation. Not wanting to potentially bugger up the threaded rods and not really sure how I could plumb and level with the stubs on the tower. I chose to install the stubs and land the tower onto the stubs.

As you can see in this sequence it went very well, Dale our crane operator was able to ever so slowly lower the assembly over the stubs. And each corner was able to with the aid of a bullpin align with the stubs.

IMG_3289
Lowering onto the base

 

IMG_3293
Aligning the bolt holes
IMG_3309
Fastening to the base
IMG_3308
John completing his leg

Antennas and feedlines

Preparing to install a dual band Diamond X50A on the west outrigger.

IMG_3328
Installing the dual band vertical

My thanks to

This project would have not have been possible without the support and help of many friends and family.

Helping on the ground special thanks go out to:

Photo of Julie Duthler
My wife Julie – Photographer

 

Photo of John Duthler
My son John – (Ground crew)
Marty, NW0L – (Ground Crew)

 

Picture of Dale Elliot
Dale, crane operator and owner Elliot construction company.

 

Next

Feedlines, grounding and lightning suppression.

73’s Jay

 

2 Comments

Leave a Reply

Your email address will not be published.


*


This site uses Akismet to reduce spam. Learn how your comment data is processed.